Boone Road Sanitary Sewer Rehabilitation

DATES: - Nov 30, 2022

Approximately 930 feet of Sanitary Sewer will be replaced along Boone Road (500 to 900). This will involve open cutting a section of Boone Road and Pipe Bursting During scheduled times of the Construction. 

Traffic will be managed to one lane (See Maintenance of Traffic Map). Be aware of traffic conditions before approaching this area.


Construction is scheduled from October 20th to November 30th.