×
Show Main Menu
Boone Road Sanitary Sewer Rehabilitation Project photo

Boone Road Sanitary Sewer Rehabilitation

DATES: - Dec 07, 2022

Approximately 930 feet of Sanitary Sewer will be replaced along Boone Road (500 to 900). This will involve open cutting a section of Boone Road and Pipe Bursting During scheduled times of the Construction. 

Traffic will be managed to one lane (See Maintenance of Traffic Map). Be aware of traffic conditions before approaching this area.


Construction is scheduled from October 20th to November 30th.


Project Updates

Project is complete Project photo
Project is complete

DATE: Feb 24, 2023

PROJECT IS UNDERWAY  Project photo
PROJECT IS UNDERWAY

DATE: Dec 07, 2022

Contact Information

Joe L Henrey

Phone Email

Check Out more City of Bryant Projects

Sign up for updates about this project