Augusta Cove Drainage Project - Phase 2

DATES: Mar 23, 2022 - Apr 19, 2022

3/18/22 Materials on-site all utilities are being located in preparation for construction to begin. Replacing of older metal culverts. 

2021- Schematic Design for Phase 2

2017 - Augusta Cove Project 1 Project Completed.  Phase Two identified. 

Project Updates

Phase #2 Complete

DATE: May 04, 2022

95% Complete

DATE: Apr 20, 2022

Project is 95% complete as of 4/20/2022

Contact Information

Engineering Dept. Daran Robinson

Phone Email