Northlake Storm Water Improvement Project Project photo

Northlake Storm Water Improvement Project

DATES: Mar 17, 2022 - Mar 17, 2030

2020 -The Northlake Road area underwent a hydraulic storm water study.  It was identified as needing significant improvements. There is severe erosion and the city considers this a public safety concern due to repeated flooding.  Estimated Cost for the project is close to $1,000,000.00. 

Project Updates

Project 65% complete  Project photo
Project 65% complete

DATE: Feb 24, 2023

Estimated completion should be around the end of March 

Project 65% complete  photo 0
Be aware of changing traffic conditions Project photo
Be aware of changing traffic conditions

DATE: Dec 08, 2022

PROJECT IS UNDERWAY Project photo
PROJECT IS UNDERWAY

DATE: Dec 07, 2022

CONSTRUCTION SHOULD BE COMPLETED MID TO LATE JANUARY

CONSTRUCTION READY TO BEGIN Project photo
CONSTRUCTION READY TO BEGIN

DATE: Nov 17, 2022

Construction is scheduled to start December 4th 2022. Construction should take about sixty days depending on the weather. 

Northlake Drainage Project - September 2022 Update Project photo
Northlake Drainage Project - September 2022 Update

DATE: Sep 28, 2022

September 2022 - City moves forward on obtaining project bids with using ARPA funds for completion.

Northlake Drainage Project - September 2022 Update photo 0
Project Maps of the Area Project photo
Project Maps of the Area

DATE: Mar 18, 2022

2021-  City is pursuing grants to assist with the cost of this project for these improvements to be funded and move forward.

September 2022 - City moves forward with obtaining Public Bids and plans on using ARPA funds to complete project.