Project Updates

FUTURE_next.exit_.roadsign_jpeg

Transportation Project Summaries

Street Projects

Heart of Bryant Reynolds Road Improvements

Status:

  • Project Completed December 2018
  • Working through punch list on final project

Bryant Parkway: Interstate 30 to Shobe Road (Project 1)

Status:

  • Earthwork is to grade from Raymar Rd to Hunter Lee. Beginning grading from Hunter Lee to Shobe Road.  
  • Paving and construction is almost completed May 2019

Schedule:

  • Construction Start Date-In Progress May 2018
  • Anticipated Completion         Summer 2019

Bryant Parkway Shobe Road to Reynolds Road (Project 2)

Status:

  • Alternative B is currently being pursued as the preferred alternative after other route were disqualified. 
  • Airport Commission has agreed to Alternative B as the best alternative route.
  • The Airport has submitted their Master Plan Update to the FAA showing the area for Bryant Parkway as Non-Aeronautical use.  Once the FAA approves the Master Plan Update, a land release request can be submitted to the FAA for approval.
  • Preliminary Bridge Plans have been submited to Union Pacific Railroad for review.  
  • 30% Roadway and Bridge plans for Bryant Parkway from Shobe to south side of bridge are complete and will be submitted to the city in November
  • Coordinating with Entergy to raise Transmission Lines where required.

Schedule:

  • Topo Surveys                      Completed
  • Parcel Surveys                    Completed
  • 30% Submittal                     In progress
  • 60% Submittal                     December 2018
  • 90% Submittal                     January 2019
  • Final Submittal                     March 2019
  • Planned Construction Start  April 2019

(N) Bryant Parkway: Highway 5 to Hilldale Road

Status:

  • Township is nearing completion but still has to pave the shared use path, finish pouring driveways, and lay sod. 

Schedule:

  • Construction                              In Progress
  • Anticipated Completion             December 2018

Bryant Pkwy/Hilldale/Hillfarm Rd Intersection Improvements

Status 

  • Top Surveys Completed
  • Garver is beginning design and will expedite design and environmental documentation in order to meet the project schedule. 

Schedule

  • Design Surveys                     Completed 
  • 30% Submittal -in progress   December 2018
  • 60% Submittal                       February 2019
  • Final Submittal                       May 2019
  • Anticipated Completion         April 2020

Bryant Parkway/ Stagecoach Road Intersection Improvements

  • The City has engaged an engineering firm to create a temporary improvement design that includes signalization.  Once the design is complete ARDOT will need to approve.  The city plans to use surplus equipment to expedite this project as much as possible. 

Hillfarm Road and Reynolds Intersection Improvement

  • Waiting on ARDOT approval for design.  The city has waived competitive bidding and we are hoping to expedite this project with intent to have installation completed this year. 

Sidewalks

Sidewalks at Elm Street and Third Street

Status:

  • 60% Construction Plans is complete
  • Design has been approved by city and will be submitted to ARDOT and Metroplan for review prior to moving forward with Final Design. 

Schedule:

  • Design Surveys                          Completed
  • 10% Submittal                            Completed
  • 60% Submittal                            Completed  
  • Final Submittal                           December 2018
  • Construction Begins                   December 2018    

imagejpeg_0

Fire Station Project Summaries

Springhill Fire Station    COMPLETE

Status:

  • Land Purchase Complete         September 2017
  • Goes out to Bid                         October 2017
  • Construction 85% Complete     August 2018
  • Construction Complete and Grand Opening held in October 2018


Schedule:

  •  Bid Review Day                        November 9, 2017  
  • City Council Approval                November 2017
  • Construction Begins                  January 2018
  • Construction Complete              COMPLETE

Hill Farm Fire Station      COMPLETE

Status:

  • Land Purchase Complete         September 2017
  • Goes out to Bid                         October 2017
  • Construction 85% Complete     August 2018
  • Construction Complete and Grand Opening held in October 2018

Schedule:

  • Bid Review Day                         November 7, 2017
  • City Council Approval                November 2017
  • Construction Begins                  January 2018
  • Construction Complete              COMPLETE

Bryant Fire Department - Fire Training Facility

  • Design 80% Completed
  • Anticipated Completion Fall 2019

           

Parks and Recreation Projects Summaries

*Project designs and timelines are subject to change as projects progress.

Mills Park Restroom Facility   COMPLETED

Status:

  • Completed

Shade Structures Bishop Park

Status:

  • Completed

New Grounds Building Bishop Park    COMPLETED

Status:

  • Complete

Schedule:

  • Completed                                      October 2018

New Park- North of Interstate

Status:

  • Land Purchase Completed- Approximately 40 acres west of Midland Park
  • Future plans include additional soccer fields along with walking and biking trails

Schedule:

  • To Be Announced


Bishop Center Remodel      COMPLETED

Status:

  • Currently Under Construction

Schedule:

  • Anticipated Completion Date            December 2018

Bishop Parking Lot and Landscaping

Status:

  • Goes out to Bid                         June 2018

Schedule:

  • City Council Approval                 June 2018
  • Work Begins                               August 2018
  • Anticipated Completion            November  2019  

Mills Parks All Inclusive Playground

Status:

  • Phase 1 Completed

Mills Park Trails Update 

  • Info coming soon!      

Ashley Park Renovation

  • Initial Design is Complete
  • Demolition is Underway
  • More Info Coming Soon!

Bryant Dog Park-- Alcoa Park

  • Location -- Alcoa Park
  • Funding has been identified May 2019
  • Initial Design is underway
  • Anticipated Completion Fall 2019

Stormwater Project Link

Stormwater ProjectsWebsite Photo Water

 

Bryant School District

Bryant School Logo

Bryant School District Facilities Moving Forward



Sign up today for Notify MeNotify MeStay up to date on ALL City News and Events